Submission of Teaching and Non-Teaching DepEd Personnel, LGUs and Stakeholders of Contextualized LRS. The CID-LRMS implements the Quality Assurance Process mandated by the Department of Education – Bureau of Education and Learning Resources (BLR) in the Design and Development, Production and Distribution of Contextualized Learning Resources (LRs).

Office or Division: Curriculum Implementation Division
Classification: Highly Technical
Type of Transaction: Government to Government (G2G)
Who may avail: Teaching and Non-Teaching Personnel, LGUs, Stakeholders
CHECKLIST OF REQUIREMENTS WHERE TO SECURE
1. Curriculum Guide (1 Original Copy and 1 Photocopy) LR Portal
2. Contextualized Material Submitted (1 Original Copy and Soft Copy) Author/ Owner
3. School/District Pre-Evaluation Online Link
4. Indorsement from the Public Schools District Supervisor or District QAD (or School Heads in the absence of PSDS) (1 Original Copy and 1 Photocopy) Office of the PSDS/Office of the CID
5. Accomplished Quality Assurance Tool LR Office
6. Accomplished Metadata Template for Cataloguing LR Office
7. Signed Sworn Certification / Anti -Plagiarism Declaration
CLIENT STEPS AGENCY ACTION FEES TO BE PAID PROCESSING TIME PERSON RESPONSIBLE
1.Prepare and submit School’s Needs Analysis (Least Mastered Competency) and LR Situational Reports 1.1. Review School’s Needs Analysis and LR Situational None 2 days School Head, School LR Coordinator, Subject Area Coordinator, Division LR Supervisor
1.2. Prepare documents for capability building None 1 day School Head, Division LR Supervisor, Writer, Illustrator, Layout Artist
2.Attend capacity building, write shop 2.1 Manage and facilitate the write shop None 5 days School Head, Division LR Supervisor, Writer, Illustrator, Layout Artist
3.Submit contextualize d LR to School Learning Resource Quality Assurance Team (SLRQAT) 3.1 Conduct level1 quality assurance of submitted LR None 5 days SLRQAT
4.Finalize LR ready for endorsement to District/Division None 1 day Writer, School Head
5.Prepare endorsement communication to District/Divisi on Quality Assurance Team 5.1 Accept endorsement communication None 3 days DLRQAT
5.2 SDO does final review if final, recommend for pilot testing if not, recommend for revision None 15 days DLRQAT
6. Integrate recommendation based on pilot testing result or resubmit revised LRs to SDO (both hard and soft copy) 6.1 SDO finalizes the Learning Resource and submits LRs in hard and softcopy to the Regional Office None 5 days Division LR Supervisor
6.2 RO finalizes the Quality Assurance of Learning Resource None 5 days Regional LREs
7. Prepare endorsement for uploading to LR portal 7.1 Upload LR to portal for online QA None 1 day Writer, School Head, Division LR Supervisor
7.2 Approve, produce and utilize to target users None 1 day Regional/ Division LR Supervisor
7.3 RO informs SDO while SDO informs the writer through written communication of the approved and uploaded LRs None 1 day Regional/ Division LR Supervisor
TOTAL: None 45 days

 